Court Renovations This Summer
Monday, July 15, 2024
To enhance community recreational spaces, a tennis court renovation project is scheduled to take place this summer at Watts Park and Berlin courts. The renovation, scheduled to unfold in several stages, aims to revitalize the tennis courts.
The court renovation at Watts Park will start first, with preliminary work estimated to span approximately three weeks for demolition and major construction activities. Following this phase, a mandatory curing period of at least three weeks will be observed before the installation of the vibrant color coating can begin.
To minimize disruptions to existing camps and activities, the renovation work at the Berlin Park courts is slated to start at the end of July. Mirroring the timeline at Watts, the renovation at Berlin is projected to last around three weeks, with an additional three-week curing period to follow suit.
The courts are expected to be fully revamped and open to the public this fall.